Meter Location and Panel Approval
Procedure to Obtain Permit and Power

Step 1: Submit this form to the Electric Utility Department, using the online form or at 150 S. 10th Street, (909) 370-5104
(Once approved, this form will be sent to the Building Department.)

Step 2: Obtain a Building Permit from the Building Department at 659 N. La Cadena Drive, (909) 370-5079
(A permit application will not be accepted until this form is on file at the Building Department)

Step 3: Pass Building Department Inspection
(The building Department will send a release to the Electric Department)

Step 4: Pass Electric Utility Inspection
(An Electric inspector will then release an order to connect service)

Step 5: Submit a Service Meter Application to Customer Service Department at 650 N. La Cadena Drive, (909) 370-5555 
(Application will not be accepted until panel has passed all inspections) 

Step 6: Panel will usually be energized within three working days once the service meter application is on file.